“Operating from Dubai Industrial City will make our products highly competitive as we will benefit from the top of the range facilities offered by the comprehensive industrial destination. In addition, the business-friendly environment will also help us focus better on further expansion.” - Souheil Hatoum, Managing Partner of United Metal Coating
“Our new facility in Dubai Industrial City is part of a strategic initiative to consolidate the supporting divisions of our umbrella group to improve efficiency across our operations.” - Sivanand Krishnan, Factory Manager, ALEC
“The decision to locate our manufacturing facility in Dubai Industrial City was taken after a meticulous assessment process. We have also found in Dubai Industrial City a willing partner that facilitates our operations.” - Lave Malhotra, General Manager, Terrazzo Group
|
|
|
|
|
Facilities Start Up Process
|
|
DI endeavors to establish a simple and clear facility start up process for companies. The DI Operations team is available to guide and assist you through the entire process. Please click here for an overview of the facility start up process.
Please click on the below links to see more information.
- Approval for tenant construction is given after the tenant has fulfilled all requirements specified in the Design and Construction Development Guidelines and obtained the respective No Objection Certificates.
- DI will also assist all tenants with a review of the Environmental Impact Assessment and Master plan, to ensure that they are compliant with Dubai Municipality and DI requirements.
- Tenants should hire a design engineering consultant registered in Dubai, well versed with the DI Design Guidelines. The design should comply with the plot land utilization requirements approved by DI and specified in the contract, for example:
- Factory 35%
- Storage 15% maximum
- Office 5% maximum
- Public Services 50% minimum.
- The tenant is also required to comply with the regulations of Dubai Municipality, Civil Defense, DEWA, RTA, and other authorities that may have an impact in developing the proposed design. Drawings must be reviewed, signed and stamped by DI.
- A No Objection Certificate is required to be obtained from DI before starting Soil Investigation Works on site.
- Contractors can mobilize only after getting Mobilization Works Commencement No Objection Certificate from DI.
- If a tenant or their appointed contractor violates DI Construction Guidelines, a Construction Deviation Report is issued and fines are imposed, including stoppage of work.
- DI enforces QHSE requirements to ensure a safe, accident free site at all stages of the construction without any adverse impact on the environment.
Companies who wish to start operations in Dubai Industrial City should contact the investor relations department at:
| Telephone |
+971 4 3643400 |
|
08:00 AM to 04:30PM on all days except Friday and Saturday |
| Fax |
+971 4 4290200 |
| Email |
This e-mail address is being protected from spambots. You need JavaScript enabled to view it
|
The investor relations team will answer your questions, provide the necessary forms, and serve as your primary point of contact to support you through the process.
|
|
|
| |
|
| |
| |